Century Construction delivered heavy construction services to the Smith County Landfill project in Carthage, Tennessee. The completion time was 6 months and the contract amount was $1,895,000 The Class 1 Wright Tract 2 project included:
• 150,000 cy of cell excavation
• 45,000 cy of clay liner and reconstructed buffer
• 25 tons of gravel drainage layer
• Includes leachate system and 7,000 sf of HDPE membrane & geocomposite drainage layer